Tank Transport Coordination
Project Brief
Project
Details
Scope
Multi-County Oversize Transport
Location
Texas — 4-County Route
Equipment Type
Cryogenic Tank on Lowboy Trailer
Key Challenge
Multi-jurisdiction permit sequencing and overnight staging coordination

Field Documentation
Tank Transport Coordination
Multi-County Oversize Transport
Site Photography
Project
Photos

Route Survey
Pre-move clearance verification

Load Movement
Active transit · pilot escort

Permit Crossing
Jurisdictional handoff point
Engineering Notes
Technical
Breakdown
DOT OS
Oversize Permit Chain
Permits obtained sequentially from all four county authorities and TxDOT. Permit conditions reviewed for move-time restrictions, escort requirements, and restricted corridors. All permits available in cab during transit.
ROUTE SURVEY
Pre-Move Highway Assessment
Licensed route survey engineer conducted full route inspection 48 hours before move date. Bridge load ratings confirmed, overhead utilities measured, intersection turn sweeps verified using scale diagram.
PILOT CARS
Front & Rear Escort
Two certified pilot car operators maintained front and rear escort throughout the route. Radio communication with transport driver maintained at all times. Pilot car operators authorized to halt traffic at uncontrolled crossings.
GPS TRACKING
Real-Time Position Monitoring
GPS tracker installed on transport vehicle provided real-time position data to project coordination team. Data archived as part of chain-of-custody documentation for the transported vessel.