LNG Storage Removal
Project Brief
Project
Details
Scope
Full Vessel Extraction & Transport
Location
Texas Gulf Coast
Equipment Type
30,000-Gal LNG Cryogenic Tank
Key Challenge
Cryogenic product residual management and critical lift sequencing

Field Documentation
LNG Storage Removal
Full Vessel Extraction & Transport
Site Photography
Project
Photos

Crane Rigging Setup
100T lift · pre-flight inspection

Vessel Pre-Purge
N₂ inerting before disconnection

Purge Rig On-Site
Continuous LEL monitoring

Heavy Transport
DOT OS/OW · SPMT trailer
Engineering Notes
Technical
Breakdown
NFPA 59A
LNG Facility Standard
Full compliance with NFPA 59A production, storage, and handling requirements. Closure documentation submitted to AHJ prior to extraction.
LEL PROTOCOL
Atmospheric Monitoring
Continuous multi-point LEL monitoring established 10 meters around the vessel throughout purging and disconnection. No cutting commenced until 0% LEL was confirmed and logged.
CRYO PURGE
Nitrogen Inerting
Residual LNG was vaporized and vented under controlled conditions. Vessel interior was nitrogen-purged and verified with calibrated gas detectors before any hot-work adjacent operations.
CRITICAL LIFT
100-Ton Crane Plan
Engineered critical lift plan accounting for vessel weight, ground-bearing pressure, outrigger pad load distribution, and wind load restrictions per ASME B30.5.
Next Step
Schedule Your
Site Audit
Our project managers are ready to assess your facility, identify regulatory requirements, and provide a fixed-scope decommissioning proposal.