Heavy Transport

Coordinated transport of a decommissioned 30,000-gallon cryogenic vessel on a specialized SPMT trailer across four Texas counties. Route survey conducted prior to move to verify bridge load ratings, overhead clearances, and intersection geometry. Pilot car convoy maintained throughout the transit.

Project Brief

Project
Details

01

Scope

Oversize/Overweight Vessel Transport

02

Location

Multi-County Texas Route

03

Equipment Type

30,000-Gal Cryogenic Tank on SPMT Trailer

04

Key Challenge

4-county permit coordination and bridge load rating verification

Heavy Transport — project brief

Field Documentation

Heavy Transport

Oversize/Overweight Vessel Transport

Site Photography

Project
Photos

Load Out

Load Out

SPMT trailer load and secure

Highway Transit

Highway Transit

Pilot car escort · active move

Bridge Crossing

Bridge Crossing

Load rating verified · reduced speed

Destination Arrival

Destination Arrival

TSDF receiving bay off-load

DOT OW/OS
Permit Type
40+ Tons
Total Load Weight
4 Counties
Route Jurisdictions
Pilot Cars
Escort Configuration

Engineering Notes

Technical
Breakdown

DOT OW/OS

Overweight/Oversize Authorization

Permits obtained from all four county jurisdictions and TxDOT. Move window restricted to daylight, non-peak traffic hours per permit conditions. All permits carried aboard the transport vehicle.

ROUTE SURVEY

Pre-Move Highway Assessment

Certified route survey completed 48 hours before move. All bridge load ratings, overhead utilities, turning radius constraints, and pavement condition flagged and mitigated before transport date.

SPMT TRAILER

Self-Propelled Modular Transporter

Hydraulic SPMT trailer used for load leveling over uneven terrain and bridge expansion joints. Trailer computer maintained vessel horizontal within 0.5° throughout transit.

CHAIN OF CUSTODY

Hazardous Manifest

DOT hazardous materials manifest maintained from load origin to licensed TSDF receiving bay. Continuous GPS tracking logged and archived as part of the project closure documentation package.