CNG Station Dismantling

Decommissioning of a multi-dispenser CNG fueling station including compression skids, high-pressure storage cascades, and dispensing equipment. All 23 energy isolation points were locked out under a multi-employer LOTO program before any mechanical disconnection was initiated.

Project Brief

Project
Details

01

Scope

Full CNG Fueling Array Teardown

02

Location

Fleet Operations Facility — Texas

03

Equipment Type

CNG Compression & Dispensing Array

04

Key Challenge

High-pressure system isolation across 23 energy isolation points

CNG Station Dismantling — project brief

Field Documentation

CNG Station Dismantling

Full CNG Fueling Array Teardown

Site Photography

Project
Photos

Cascade Isolation

Cascade Isolation

High-pressure LOTO application

Array Disconnect

Array Disconnect

Mechanical disconnection sequence

Compressor Removal

Compressor Removal

Skid rigging for haul-away

Site Clearance

Site Clearance

Post-removal site condition

3,600 PSI
System Operating Pressure
NFPA 52
Compliance Standard
LOTO
Energy Isolation Protocol
DOT
Transport Manifest

Engineering Notes

Technical
Breakdown

3,600 PSI

High-Pressure Isolation

System operating pressure of 3,600 PSI required staged depressurization through the cascade from dispensing pressure down to atmospheric. Each stage verified with calibrated pressure gauges before proceeding.

NFPA 52

CNG Facility Compliance

Full NFPA 52 CNG vehicular fuel systems standard compliance. Closure notification submitted to local fire marshal and AHJ. All permits obtained before mechanical disconnection.

LOTO PROGRAM

Multi-Employer Isolation

23 individual energy isolation points identified, documented, and controlled under a multi-employer LOTO program. Group lockout hasps applied at each point. Zero-energy state verified by field supervisor before each work phase.

DOT MANIFEST

Regulated Transport

CNG pressure vessels transported as regulated hazardous materials under DOT 49 CFR. All manifests, placarding, and driver certifications confirmed before load movement.